Rabu, 04 Mei 2011

RAB Sem 4

SOAL TES SEMESTER 4

DIKLAT/KOMPETENSI : GK1/RAB1 THN PEL : 2010/2011

KELAS /KOMP. KEAH : XI / TKBB WAKTU : 90 menit


I. Kerjakanlah Data Rencana Proyek dibawah ini sesuai dengan nomor absensi Anda.

No

Uraian/Jenis Pekerjaan

Nomor Absensi Siswa

1

Pengukuran dan Pemasangan Bouwplank

1, 6, 11, 16, 21, 26, 31

2

Galian tanah biasa sedalam 1m

1, 6, 11, 16, 21, 26, 31

3

Mengurug Pasir Urug

1, 6, 11, 16, 21, 26, 31

4

Pasangan pondasi batu kosong (Anstamping)

1, 6, 11, 16, 21, 26, 31

5

Pasangan Pondasi batu kali 1Pc : 8Ps

1, 6, 11, 16, 21, 26, 31

6

Pasangan bata merah tebal 1/2 bata, 1Pc: 3Ps

1, 6, 11, 16, 21, 26, 31

7

Pasangan bata merah tebal 1/2 bata, 1Pc: 8Ps

1, 6, 11, 16, 21, 26, 31

8

Plesteran 1 Pc : 3 Ps, Tebal 15mm

2, 7, 12, 17, 22, 27, 32

9

Plesteran 1 Pc : 8 Ps. Tebal 15 mm

2, 7, 12, 17, 22, 27, 32

10

Pekerjaan Beton Tumbuk 1Pc:3Ps:5Kr

2, 7, 12, 17, 22, 27, 32

11

Pekerjaan Beton 1Pc:2Ps:3Kr

2, 7, 12, 17, 22, 27, 32

12

Pembesian dengan besi polos atau ulir

2, 7, 12, 17, 22, 27, 32

13

Pasang bekisting untuk sloof (3 kali pakai)

2, 7, 12, 17, 22, 27, 32

14

Pasang bekisting untuk kolom (3 kali pakai)

3, 8, 13, 18, 23, 28

15

Pasang bekisting untuk balok (3 kali pakai)

3, 8, 13, 18, 23, 28

16

Pekerjaan kusen pintu dan jendela kayu (kamper)

3, 8, 13, 18, 23, 28

17

Pekerjaan daun pintu dan jendela kaca kayu (kamper)

3, 8, 13, 18, 23, 28

18

Pekerjaan pintu panil kayu (kamper)

3, 8, 13, 18, 23, 28

19

Pasang jalusi Kusen Kayu (Kamfer)

3, 8, 13, 18, 23, 28

20

Pasangan konstruksi Kuda-kuda kayu (kamper)

4, 9, 14, 19, 24, 29

21

Pasang Gording/Nok/Murplat Kayu (Kamper)

4, 9, 14, 19, 24, 29

22

Pasang kaso + reng kayu (Kamper)

4, 9, 14, 19, 24, 29

23

Pasang lisplank (3 x 20) cm kayu (kamper)

4, 9, 14, 19, 24, 29

24

Pasang genteng bubung palentong

4, 9, 14, 19, 24, 29

25

Pasang genteng palentong

4, 9, 14, 19, 24, 29

26

Pasang rangka langit-langit (1,00 x 1,00) m, kayu (kamper)

5, 10, 15, 20, 25, 30

27

Langit-langit Eternit (1,00 x 1,00) m, Tebal 5 mm

5, 10, 15, 20, 25, 30

28

Pengecatan bid kayu baru (1 lps plamur, 1 lps cat dsr, 2 lps cat pnutup)

5, 10, 15, 20, 25, 30

29

Pengecatan Tembok/Eternit baru (1 lps plamur, 1 lps cat dsr, 2 lps cat pnutup)

5, 10, 15, 20, 25, 30

30

Pasang lantai keramik 30 x 30 KW 1

5, 10, 15, 20, 25, 30

31

Pasang Engsel Pintu

5, 10, 15, 20, 25, 30

Hitunglah :

  1. Daftar Analisa Satuan Pekerjaan (sesuai dengan nomor absensi Anda).
  2. Rencana Anggaran Biaya (sesuai dengan nomor absensi Anda).

Catatan :

  1. Kerjakan pada lembar soal/formulir yang sudah disediakan.
  2. Semua lembar soal/formulir dikumpulkan ke Pengawas Ruang.

DAFTAR ANALISA SATUAN PEKERJAAN
Kode Koefisien Satuan Pekerjaan/Material Harga HOK/ Harga Jumlah
Bahan (Rp) Semua (Rp) Harga (Rp)
SNI A.6.4 1M2 Pengukuran dan Pemasangan Bouwplank
0,0120 M3 Kayu 5/7
0,0070 M3 Papan Bouwplank
0,0200 Kg Paku
0,0050 Org/hr mandor
0,0100 Org/hr Kep Tukang
0,1000 Org/hr Tukang
0,1000 Org/hr Pekerja
RSNI B.6.1 1M3 Galian tanah biasa sedalam 1m
0,7500 Org/hr Pekerja
0,0250 Org/hr Mandor
RSNI B.6.11 1M3 Mengurug Pasir Urug
1,2000 m3 Pasir urug
0,3000 Org/hr Pekerja
0,0100 Org/hr Mandor
RSNI C.6.9 1M3 Pasangan pondasi batu kosong (Anstamping)
1,2000 M3 Batu belah
0,4320 M3 Pasir urug
0,7800 Org/hr Pekerja
0,3900 Org/hr Tukang batu
0,0390 Org/hr Kepala Tukang
0,0390 Org/hr Mandor
RSNI C.6.5 1M3 Pasangan Pondasi batu kali 1Pc : 8Ps
1,2000 M3 Batu belah putih
1,8200 Zak Semen Portland
0,5840 M3 Pasir Pasang
1,5000 Org/hr Pekerja
0,6000 Org/hr Tukang Batu
0,0600 Org/hr Kepala Tukang
0,0750 Org/hr Mandor
RSNI D.6.8 1 M2 Pasangan bata merah tebal 1/2 bata, 1Pc: 3Ps
70,0000 Buah Bata merah
0,2874 Zak Semen Portland
0,0400 M3 Pasir Pasang
0,0300 Org/hr Pekerja
0,1000 Org/hr Tukang batu
0,0100 Org/hr Kepala Tukang
0,0150 Org/hr Mandor
RSNI D.6.12 1 M2 Pasangan bata merah tebal 1/2 bata, 1Pc: 8Ps
70,0000 Buah Bata merah
0,1300 Zak Semen Portland
0,0500 M3 Pasir Pasang
0,3000 Org/hr Pekerja
0,1000 Org/hr Tukang batu
0,0100 Org/hr Kepala Tukang
0,0150 Org/hr Mandor
DAFTAR ANALISA SATUAN PEKERJAAN
Kode Koefisien Satuan Pekerjaan/Material Harga HOK/ Harga Jumlah
Bahan (Rp) Semua (Rp) Harga (Rp)
RSNI E.6.3 1M2 Plesteran 1 Pc : 3 Ps, Tebal 15mm
0,1555 Zak Semen Portland
0,0230 M3 Pasir Pasang
0,2000 Org/hr Pekerja
0,1500 Org/hr Tukang batu
0,0150 Org/hr Kepala Tukang
0,0100 Org/hr Mandor
RSNI E.6.8 1 M2 Plesteran 1 Pc : 8 Ps. Tebal 15 mm
0,0691 Zak Semen Portland
0,0290 M3 Pasir Pasang
0,2000 Org/hr Pekerja
0,1500 Org/hr Tukang batu
0,0150 Org/hr Kepala Tukang
0,0100 Org/hr Mandor
SNI G.6.1 1M3 Pekerjaan Beton Tumbuk 1Pc:3Ps:5Kr
4,3600 Zak Sement Portland
0,5200 M3 Pasir beton
0,8700 M3 Koral Beton
200,0000 l Air
1,6500 Org/hr Pekerja
0,2500 Org/hr Tukang Batu
0,0700 Org/hr Kepala Tukang
0,0800 Org/hr Mandor
SNI G.6.13 1M3 Pekerjaan Beton 1Pc:2Ps:3Kr
6,7200 Zak Sement Portland
0,5400 m3 Pasir beton
0,8100 m3 Koral Beton
200,0000 l Air
2,0000 Org/hr Pekerja
0,3500 Org/hr Tukang Batu
0,0350 Org/hr Kepala Tukang
1,0000 Org/hr Mandor
RSNI G.6.17 10 Kg Pembesian dengan besi polos atau ulir
10,5000 Kg Besi beton (polos/ulir)
0,1500 Kg Kawat beton
0,0700 Org/hr Pekerja
0,0700 Org/hr Tukang besi
0,0070 Org/hr Kepala tukang
0,0040 Org/hr Mandor
1 KG Pembesian
RSNI G.6.21 1M2 Pasang bekisting untuk sloof (3 kali pakai)
0,0150 M3 Kayu cetakan/begisting
0,3000 Kg Paku biasa 2" - 5"
0,1000 Lt Minyak bekisting
0,5200 Org/hr Pekerja
0,2600 Org/hr Tukang kayu
0,0260 Org/hr Kepala tukang
0,0260 Org/hr Mandor
DAFTAR ANALISA SATUAN PEKERJAAN
Kode Koefisien Satuan Pekerjaan/Material Harga HOK/ Harga Jumlah
Bahan (Rp) Semua (Rp) Harga (Rp)
RSNI G.6.22 1 M2 Pasang bekisting untuk kolom (3 kali pakai)
0,0133 M3 Kayu cetakan/begisting
0,4000 Kg Paku biasa 2" - 5"
0,2000 Lt Minyak bekisting
0,0150 M3 Balok kayu kalimantan
0,3500 Lbr Plywood tebal 9 mm
2,0000 btg Dolken kayu galam diamt 8-10/4m
0,6600 Org/hr Pekerja
0,3300 Org/hr Tukang kayu
0,0330 Org/hr Kepala tukang
0,0330 Org/hr Mandor
RSNI G.6.23 1M2 Pasang bekisting untuk balok (3 kali pakai)
0,0133 M3 Kayu cetakan/begisting
0,4000 Kg Paku biasa 2" - 5"
0,2000 Lt Minyak bekisting
0,0180 M3 Balok kayu kalimantan
0,3500 Lbr Plywood tebal 9 mm
2,0000 Btg Dolken kayu 8-10/4m
0,6600 Org/hr Pekerja
0,3300 Org/hr Tukang kayu
0,0330 Org/hr Kepala tukang
0,0330 Org/hr Mandor
RSNI F.6.2 1M3 Pekerjaan kusen pintu dan jendela kayu (kamper)
1,2000 M3 Kayu (kamper) balok
1,2500 Kg Paku
6,0000 Org/hr Pekerja
18,0000 Org/hr Tukang Kayu
2,0000 Org/hr Kepala tukang kayu
0,3000 Org/hr Mandor
RSNI F.6.6.b 1M2 Pekerjaan daun pintu dan jendela kaca kayu (kamper)
0,0240 M3 Kayu (kamper) ram
0,3000 Kg Lem Kayu
0,0800 Org/hr Pekerja
2,0000 Org/hr Tukang kayu
0,2000 Org/hr Kepala Tukang
0,0400 Org/hr Mandor
RSNI F.6.5.b 1 M2 Pekerjaan pintu panil kayu (kamper)
0,0400 M3 Kayu (kamper) papan
0,5000 Kg Lem Kayu
1,0000 Org/hr Pekerja
2,5000 Org/hr Tukang kayu
0,2500 Org/hr Kepala tukang
0,0500 Org/hr Mandor
RSNI F.6.10.b 1 M2 Pasang jalusi Kusen Kayu (Kamfer)
0,0600 M3 Kayu (kamper) ram
0,1500 Kg Paku biasa 1/2"-1"
0,5000 Org/hr Pekerja
2,0000 Org/hr Tukang kayu
0,2000 Org/hr Kepala Tukang
0,0250 Org/hr Mandor
DAFTAR ANALISA SATUAN PEKERJAAN
Kode Koefisien Satuan Pekerjaan/Material Harga HOK/ Harga Jumlah
Bahan (Rp) Semua (Rp) Harga (Rp)
RSNI F.6.13.b 1M3 Pasangan konstruksi Kuda-kuda kayu (kamper)
1,1000 M3 Kayu (kamper) balok
15,0000 Kg Besi strip
5,6000 Kg Paku biasa 2"-5"
4,0000 Org/hr Pekerja
12,0000 Org/hr Tukang Kayu
1,2000 Org/hr Kepala tukang
0,2000 Org/hr Mandor
RSNI F.6.15b 1 M3 Pasang Gording/Nok/Murplat Kayu (Kamper)
1,1000 m3 Kayu (kamper) balok
3,0000 kg Paku
15,0000 kg Besi strip
2,4000 Org/hr Pekerja
7,2000 Org/hr Tukang Kayu
0,7200 Org/hr Kepala tukang
0,1200 Org/hr Mandor
SNI F.6.31.b 1M2 Pasang kaso + reng kayu (Kamper)
0,0120 M3 Kayu (kamper) Usuk
0,1500 Kg Paku biasa 2"-5"
0,1000 Org/hr Pekerja
0,1000 Org/hr Tukang Kayu
0,0100 Org/hr Kepala tukang
0,0050 Org/hr Mandor
RSNI F.6.21.b 1 M1 Pasang lisplank (3 x 20) cm kayu (kamper)
0,0108 M3 Kayu (kamper) papan
0,1000 Kg Paku biasa 2" - 5"
0,1000 Org/hr Pekerja
0,2000 Org/hr Tukang kayu
0,0250 Org/hr Kepala tukang
0,0050 Org/hr Mandor
SNI H.6.4 1M2 Pasang genteng bubung palentong
5,0000 Bh Genteng bubung palentong
0,1600 Zak Semen Portland
0,0320 M3 Pasir Pasang
0,4000 Org/hr Pekerja
0,2000 Org/hr Tukang kayu
0,0200 Org/hr Kepala tukang
0,0020 Org/hr Mandor
SNI H.6.1 1M2 Pasang genteng palentong
25,0000 Bh Genteng palentong
0,1500 Org/hr Pekerja
0,0750 Org/hr Tukang kayu
0,0080 Org/hr Kepala tukang
0,0080 Org/hr Mandor
DAFTAR ANALISA SATUAN PEKERJAAN
Kode Koefisien Satuan Pekerjaan/Material Harga HOK/ Harga Jumlah
Bahan (Rp) Semua (Rp) Harga (Rp)
SNI F.6.39.b 1M2 Pasang rangka langit-langit (1,00 x 1,00) m, kayu (kamper)
0,0120 M3 Kayu kamper usuk
0,1000 Kg Paku biasa 2" - 5"
0,1500 Org/hr Pekerja
0,2500 Org/hr Tukang kayu
0,0250 Org/hr Kepala tukang
0,0750 Org/hr Mandor
RSNI I.6.1 1M2 Langit-langit Eternit (1,00 x 1,00) m, Tebal 5 mm
1,1000 Lbr Eternit (1,00 x 1,00) m Tebal 5mm
0,0100 Kg Paku
0,0300 Org/hr Pekerja
0,0700 Org/hr Tukang kayu
0,0070 Org/hr Kepala tukang
0,0020 Org/hr Mandor
SNI N.6.7 1 M2 Pengecatan bid kayu baru (1 lps plamur, 1 lps cat dsr, 2 lps cat pnutup)
0,1500 Kg Plamir
0,1700 Kg Cat dasar
0,1700 Kg Cat penutup 2x
0,0700 Org/hr Pekerja
0,0750 Org/hr Tukang Cat
0,0075 Org/hr Kepala tukang
0,0025 Org/hr Mandor
SNI N.6.14 1 M2 Pengecatan Tembok/Eternit baru (1 lps plamur, 1 lps cat dsr, 2 lps cat pnutup)
0,1000 Kg Plamir
0,1000 Kg Cat dasar
0,2600 Kg Cat penutup 2x
0,0200 Org/hr Pekerja
0,0630 Org/hr Tukang cat
0,0063 Org/hr Kepala tukang
0,0025 Org/hr Mandor
RSNI M.6.35 1 M2 Pasang lantai keramik 30 x 30 KW 1
1,0791 M2 Ubin keramik 30 x 30
0,2000 Zak Semen Portland
0,0450 M3 Pasir pasang
1,5000 Kg Semen warna
0,6200 Org/hr Pekerja
0,3500 Org/hr Tukang batu
0,0350 Org/hr Kepala tukang
0,0300 Org/hr Mandor
SNI L.6.5 1 Bh Pasang Engsel Pintu
1,0000 Bh Engsel pintu
0,0150 Org/hr Pekerja
0,1500 Org/hr Tukang kayu
0,0150 Org/hr Kepala tukang
0,0008 Org/hr Mandor
DAFTAR HARGA SATUAN BAHAN
No. Jenis Tenaga Volume Satuan Harga (Rp)
1 Besi Strip 1 kg 15.000,00
2 Besi beton 1 kg 15.000,00
3 Batu bata 1 bh 500,00
4 Batu belah pondasi 10-15 1 m3 100.000,00
5 Batu pecah mesin/koral 2/3 1 m3 200.000,00
6 Cat kayu 1 kg 40.000,00
7 Cat tembok 1 kg 15.000,00
8 Eternit 4-5 mm (100x100) 1 lbr 15.000,00
9 Engsel Jendela 1 unit 20.000,00
10 Kait angin 1 unit 10.000,00
11 Engsel pintu 1 unit 25.000,00
12 Kunci tanam 1 bh 75.000,00
13 Genteng bubungan Plentong 1 bh 2.500,00
14 Genteng Plentong 1 bh 750,00
15 Kapur pasang 1 m3 210.000,00
16 Kawat beton 1 kg 17.500,00
17 Kayu bangkirai 8/12 dan 6 /12 1 m3 6.500.000,00
18 Kayu bangkirai usuk 5/7 1 m3 6.500.000,00
19 Kayu bangkirai reng 2/3 1 m3 6.500.000,00
20 Kayu bangkirai ram pintu 1 m3 7.000.000,00
21 Kayu bangkirai ram jendela 1 m3 7.000.000,00
22 Kayu bengkirai papan 20 cm 1 m3 7.000.000,00
23 Kayu kamper 8/12 dan 6/12 1 m3 7.000.000,00
24 Kayu kamper usuk 5/7 1 m3 7.000.000,00
25 Kayu kamper ram pintu 1 m3 7.500.000,00
26 Kayu kamper ram jendela 1 m3 7.500.000,00
27 Kayu kamper papan 20 1 m3 7.500.000,00
28 Kayu perancah 1 m3 1.000.000,00
29 Kayu cetakan/begisting 1 m3 1.000.000,00
30 Kayu Jati Balok 1 m3 15.000.000,00
31 Kaca 5 mm 1 m2 80.000,00
32 List kayu 2/3 1 m1 5.000,00
33 Minyak pelumas/begisting 1 ltr 10.000,00
34 Multiplek 9 mm 1 lbr 150.000,00
35 Plywood 9 mm 1 lbr 150.000,00
36 Dolken kayu galam 1 batang 20.000,00
37 Paku reng 1 kg 20.000,00
38 Paku usuk 1 kg 17.500,00
39 Paku eternit 1 kg 22.500,00
40 Pasir beton 1 m3 150.000,00
41 Pasir pasang 1 m3 100.000,00
42 Pasir urug 1 m3 75.000,00
43 Plamir 1 kg 15.000,00
44 Semen PC (50 kg) 1 zak 50.000,00
45 Semen PC (50 kg) 1 kg 2.000,00
46 Tegel Keramik 30 x 30 (KW 1) 1 m2 50.000,00
47 Semen warna 1 kg 4.000,00
48 Bak mandi Fiber 1 Buah 350.000,00
49 Urinoir 1 Buah 300.000,00
50 Kloset Jongkok 1 Buah 70.000,00
51 Lem Kayu 1 kg 10.000,00
52 Air 1 l 50,00


DAFTAR HARGA SATUAN TENAGA/UPAH
No. Jenis Tenaga Volume Satuan Harga (Rp)
1 Mandor 1 HOK Rp 45.000,00
2 Kepala tukang 1 HOK Rp 45.000,00
3 Tukang 1 HOK Rp 40.000,00
4 Pekerja 1 HOK Rp 25.000,00


DAFTAR VOLUME KEBUTUHAN TIAP JENIS PEKERJAAN
No Uraian/Jenis Pekerjaan Volume/
Kebutuhan
1 Pengukuran dan Pemasangan Bouwplank 120,00 M2
2 Galian tanah biasa sedalam 1m 75,00 M3
3 Mengurug Pasir Urug 5,00 M3
4 Pasangan pondasi batu kosong (Anstamping) 10,00 M3
5 Pasangan Pondasi batu kali 1Pc : 8Ps 50,00 M3
6 Pasangan bata merah tebal 1/2 bata, 1Pc: 3Ps 5,00 M2
7 Pasangan bata merah tebal 1/2 bata, 1Pc: 8Ps 100,00 M2
8 Plesteran 1 Pc : 3 Ps, Tebal 15mm 20,00 M2
9 Plesteran 1 Pc : 8 Ps. Tebal 15 mm 400,00 M2
10 Pekerjaan Beton Tumbuk 1Pc:3Ps:5Kr 2,00 M3
11 Pekerjaan Beton 1Pc:2Ps:3Kr 20,00 M3
12 Pembesian dengan besi polos atau ulir 2.000,00 Kg
13 Pasang bekisting untuk sloof (3 kali pakai) 60,00 M2
14 Pasang bekisting untuk kolom (3 kali pakai) 120,00 M2
15 Pasang bekisting untuk balok (3 kali pakai) 80,00 M2
16 Pekerjaan kusen pintu dan jendela kayu (kamper) 5,00 M3
17 Pekerjaan daun pintu dan jendela kaca kayu (kamper) 24,00 M2
18 Pekerjaan pintu panil kayu (kamper) 8,00 M2
19 Pasang jalusi Kusen Kayu (Kamfer) 6,00 M2
20 Pasangan konstruksi Kuda-kuda kayu (kamper) 4,00 M3
21 Pasang Gording/Nok/Murplat Kayu (Kamper) 5,00 M3
22 Pasang kaso + reng kayu (Kamper) 350,00 M2
23 Pasang lisplank (3 x 20) cm kayu (kamper) 120,00 M'
24 Pasang genteng bubung palentong 50,00 M'
25 Pasang genteng palentong 350,00 M2
26 Pasang rangka langit-langit (1,00 x 1,00) m, kayu (kamper) 100,00 M2
27 Langit-langit Eternit (1,00 x 1,00) m, Tebal 5 mm 100,00 M2
28 Pengecatan bid kayu baru (1 lps plamur, 1 lps cat dsr, 2 lps cat pnutup) 60,00 M2
29 Pengecatan Tembok/Eternit baru (1 lps plamur, 1 lps cat dsr, 2 lps cat pnutup) 420,00 M2
30 Pasang lantai keramik 30 x 30 KW 1 120,00 M2
31 Pasang Engsel Pintu 24,00 Bh


RENCANA ANGGARAN BIAYA (RAB)
NO Uraian Pekerjaan Volume Sat Pek Analisa Harga Sat. Pek.(Rp). Jumlah Total
(Rp)
Jumlah Keseluruhan

Selamat Mengerjakan

Tidak ada komentar:

Posting Komentar